The City of Grand Forks reconstruction project on Belmont Road from Rivers Edge Drive to 55th Avenue South will begin on Monday, June 14.
During the first week of the project, crews will be doing some preliminary utility work. Flaggers will be in place, but Belmont Road will remain open with possible traffic delays from Rivers Edge Dr. to 55th Avenue South.
The closure on Belmont Road will come in 2 phases.
Starting the week of June 21, crews will close Belmont Road from Rivers Edge Drive to Desiree Drive and will also close access to Belmont Road from Christian Drive. This is phase 1 of the reconstruction and is expected to be complete by late August.
Phase 2 of the reconstruction will close Belmont Road from Desiree Drive to 55th Avenue Sout. Phase 2 of the project is expected to be complete by late October, weather permitting.