Skip to content
Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

ADVERTISE WITH US | EMAIL: KROX@RRV.NET

CROOKSTON HIGH SCHOOL MULTI-USE FACILITY PROJECT GOING AS PLANNED

Construction of Crookston High School’s new multi-use sports facility began earlier in the year, and the project is progressing well.

The project began on April 15, 2024, with the initial groundbreaking of the area. The original deadline set for the overall project was for when Crookston High School hosts its first football game of the season. 

The construction site currently has many moving pieces. This week, the major update will be the addition of light posts for the multi-use facility.

“Things are going well right now, but we’ve had a lot of rain. Right now, at this point, June 25, we are still on track to hopefully have this ready to go by the first home football game on September 13,” said Crookston Superintendent of Schools, Randy Bergquist. “Probably tomorrow, they are supposed to start putting in the light poles, and the electric work is being worked on. We already worked on the drain tile, so that’ll help for years down the road, but it will come with water, flooding, and different types of things like that. The drain tile is already put in,” said Bergquist. “My self and Nate Lubarski, our Activities Director, has also done a great job. We probably communicate every day, and during the evenings, we go up there to check the progress and take pictures. But so far, I am pleasantly surprised with the rain that we are still on track. If it rains 10 days out of the next 14, that could mean a different story, but my goal the whole time was to have this ready to go before the first home football game and first home soccer game.” 

Remain work for the project is as follows- 

  • General Work and Labor, such as framing, rock/tape, and partitions, began June 18 and will go on August 30
  • Electrical work began on April 22 and will go on until August 9
  • Earthwork started April 15 and will run through August 2
  • Concrete-building/Site Surfacing started on April 29 and will through July 9
  • Asphalt Paving started June 17 and will go on until July 30
  • Landscaping started August 5 and will go through August 9
  • Site Fencing started on April 22 and will go on until August 30
  • Sprint Turf installation to begin July 29-August 22
  • Track installation to begin July 31- August 8
  • Grandstand installation started June 10 and will go on until July 26

 